Riveting the first rib.Timer icon4h

December 14, 2024

Today I started riveting the ribs to the skin.

Again, I followed the Van's RV Fuel Tank Construction Tips video. I was working alone, so I did not take many photos.

Since some of the rivets (the forward ones) are kind of hard to reach, I used my swiveling mushroom set. It kind of worked, but I found that it does not squeeze rivets all too well, and gun tends to slide away (because of the swivel). For the next rib, I will try to use my regular mushroom set.

This was the end result.

Rib is fully riveted.

The view from the back.

Outside view.

It took me about 2 hours of time to install a single rivet. Since I still had sealant left, I used it to close the tooling hole on the outboard rib. I used AN470A6 rivet, a soft one, as the structural strength is not important for that application, and it is much easier to set the soft rivet.

The tooling hole.

The rivet covering the tooling hole.

Finally, I riveted the anti-rotation bracket, too.

The bracket is sealed.

The outside view of the bracket.

And that was the end of the session. I had to discard probably the majority of the sealant cartridge, but it's so convenient, so I'll keep using them.